In-house trades or subcontractors, and why it changes your renovation
A bathroom needs about six specialist trades, and how a builder engages them changes your dates more than it changes your price. Subcontracting is normal in this industry. The Australian Bureau of Statistics found that 21 per cent of people working in construction are independent contractors, the highest share of any industry except administrative services, and among technicians and trades workers it is around 15 per cent. The majority of our trades are employed rather than hired job by job. That is the main reason we hold three to four weeks on site.
My name is Michael. I am a registered builder and a licensed plumber, and I project manage the trades on every bathroom we do across Berwick, Officer, Pakenham, Narre Warren, Beaconsfield and Clyde North.
What it affects | Trades employed by the builder | Trades subcontracted job by job |
Who sets the day they arrive | The builder, from his own diary | The subcontractor, around his other clients |
If a stage runs over | The next trade is moved by the same person | The next trade may already be committed elsewhere |
Coming back for a small fix | Booked internally | Depends on the subcontractor’s availability and goodwill |
Consistency between jobs | The same people, working the same way | Varies with who was free that week |
Who is liable to you | The builder who holds your contract | The builder who holds your contract |
Who you raise a problem with | The builder | The builder, who then has to raise it with someone else |
Both arrangements are legal and both are common. The difference is in scheduling and in what happens after handover.
What subcontracting means
A subcontractor is a tradesman who runs his own business and is hired for one stage of one job. Your builder holds the contract with you, then engages a tiler, a waterproofer, a plasterer and the rest as separate businesses, each with their own diary, their own insurance and their own other customers.
An employed trade is on the builder’s payroll. The builder pays superannuation and work cover for that person, carries them between jobs, and decides where they are on any given day. Some companies employ their trades and some subcontract every one of them, and plenty of businesses sit somewhere in between.
There are sound reasons the industry leans towards subcontracting. Bathroom work is specialised, and a waterproofer who does nothing else all year is fast and good at it. Demand moves around, so carrying a full crew through a slow month is a real cost. A small builder cannot keep six trades busy on his own work. None of that is cutting corners. It is how most of the industry is built.
Employing a trade is a standing cost rather than a job by job one. Under the Building and Construction General On-site Award, a casual labourer on the lowest classification is $33.34 an hour from 1 July 2026. Add 12 per cent superannuation and about 3 per cent work cover and it costs close to $40 an hour to have that person on site, before any skill is involved, and a qualified tradesman is well above it. That cost continues whether or not there is a bathroom to work in that week, which is why a builder only employs trades if he has enough work to keep them moving.
Where it shows up: your dates
A bathroom has to be built in a fixed order. The waterproofer cannot start until the rough-in and sheeting are done. The tiler cannot start until the membrane has cured. The plumber cannot fit off until the grout has hardened. The shower screen cannot be measured until the tiles are on. Every trade waits on the one before it.
When the trades are employed, the builder moves them himself. If demolition finds rot and the job loses two days, the same person who booked the tiler moves the tiler, and the plumber behind him, and the whole schedule slides two days and no further.
When they are subcontracted, that same two day slip means ringing a tiler who has already promised Thursday to someone else. He is not being difficult. He has a business to run and a diary that was full before your bathroom slipped. So Thursday becomes the following Tuesday, and the plumber booked behind the tiler now cannot come until the Friday after that. A two day problem becomes a ten day problem, and it happens in the gaps rather than in the work.
This is the reason renovation timelines blow out far more often than renovation budgets do.
Where it shows up: after handover
The second difference arrives months later, when something small needs attention. A silicone bead that has shrunk, a screen that has dropped slightly, a mixer that drips.
With employed trades, that visit is a diary entry. With subcontracted trades, the builder has to find a tradesman who has moved on to other work and ask him to come back to a job he finished and was paid for. Most will come back, some take a while, and a few have stopped answering, particularly where there was a disagreement over the invoice at the time.
This is worth understanding before you sign rather than after, because the aftercare on a bathroom matters more than people expect. The room is used twice a day by everyone in the house.
There is a simple thing that helps either way. Ask at handover for the names and licence numbers of the plumber and the electrician who worked on your bathroom, and keep them with your certificates and your warranty. If you sell the house, or if something needs attention in four years, that piece of paper is what turns a vague problem into a phone call. Builders who run organised jobs hand it over without being asked.
Who is actually responsible
The way a builder engages his trades does not change who owes you the work.
Whoever holds your contract is responsible for the work, whether or not the person who did it is on their payroll.
Work over $10,000 requires a major domestic building contract, and work over that value must be carried out by a registered builder. Work valued at more than $20,000 requires Home Warranty, which replaced Domestic Building Insurance on 1 July 2026. Cover starts when you sign the contract, runs to $400,000, and applies where the work is incomplete, defective or non-compliant and the builder is unable or unwilling to fix it. In Victoria a building action must be brought within ten years of the occupancy permit being issued, or where none issues, the certificate of final inspection. All of that attaches to the business named on your contract.
So the argument for employed trades is not that a subcontractor leaves you unprotected. It is that having to chase the work through two businesses instead of one takes longer, and time is what people find hardest when their bathroom is the problem.
One thing does change. A subcontractor still needs to be licensed for his own trade. The plumbing must be done by a licensed plumber who issues a Compliance Certificate of Plumbing Work for any plumbing work valued at $750 or more, and the electrical work must come with a Certificate of Electrical Safety. Those certificates are issued by the individual who did the work, not by the builder, and you should receive both regardless of who employed him.
What it does not tell you
A builder who employs his trades is not automatically better than one who subcontracts. There are excellent subcontractors who have worked with the same builder for fifteen years, who turn up when they say they will, and who go back to fix things because their reputation depends on it. There are employed tradesmen who are ordinary.
What employment gives you is control of the diary and one person to ring. What a long-standing subcontract relationship gives you is much the same thing, as long as the relationship is real. The question to ask is not which model the builder uses. It is how long he has been working with the people who will be in your house.
How we do it
The majority of our trades are employed rather than hired job by job, and I project manage them myself. Everyone on your bathroom is a specialist, and my job is to make sure each one arrives in the right order, on the right day, with the room ready for them.
That coordination is a real line in your price, and it is the part people are most surprised to be paying for. It is also the difference between a job that runs for three to four weeks and one that runs for six with nobody on site half of those days. You pay with money or you pay with time.
How it shows up in your payment schedule
Payment stages are usually tied to the work being finished, so the way trades are engaged reaches your bank account as well as your calendar.
On a contract over $20,000 the deposit is capped at 5 per cent in Victoria, so the most you can be asked for on a $30,000 bathroom is $1,500. The rest is paid in stages as the work is completed. A schedule that asks for a large payment before a stage is done is worth questioning whoever the trades belong to, and a builder who needs money up front to pay a subcontractor who has not started is telling you something about the state of the business.
Ask for the payment stages in writing next to the work each one covers. A fair schedule pays for finished work, and it should be possible to walk into the room and see what you are paying for.
What to ask any renovator
None of these questions require you to know anything about building, and the answers tell you more than a price does.
Ask who will actually be in your house, and whether they are employed or subcontracted. Ask how long the builder has worked with them. Ask who moves the schedule if a stage runs over, and what happened on the last job where that occurred. Ask who you ring six months after handover if something needs attention, and how quickly that visit usually happens. Ask for the plumber’s and electrician’s licence details and check them on the building regulator’s public register, which also lists prosecutions and disciplinary action. One builder on that register was fined $70,000 for carrying out major domestic building work without insurance while unregistered.
A builder who runs an organised job will answer all of that in a couple of minutes, because it is how he thinks about his week. Vagueness on who is coming and when is the answer to your question.
Take the questions with you
FAQ
What is the difference between an in-house trade and a subcontractor? An in-house trade is employed by the builder and paid through his payroll. A subcontractor runs his own business and is engaged for one stage of one job, with his own diary and other customers.
Is subcontracting normal in bathroom renovation? Yes. The Australian Bureau of Statistics found 21 per cent of construction workers are independent contractors, the highest share of any industry except administrative services. Some companies employ their trades and some subcontract every one of them.
Does it change the price of my bathroom? Less than people expect. It changes the schedule and the aftercare more than it changes the quote.
Why do subcontracted jobs take longer? Because every trade waits on the one before it. If a stage slips two days, a subcontractor who has already committed those days elsewhere cannot simply move, so a two day problem can become a ten day one.
Who is responsible if something goes wrong? The business named on your contract, regardless of who did the work. Work over $10,000 requires a major domestic building contract with a registered builder, and work valued at more than $20,000 requires Home Warranty cover.
Do subcontractors need their own licences? Yes. A licensed plumber must issue a Compliance Certificate of Plumbing Work for plumbing valued at $750 or more, and the electrician must issue a Certificate of Electrical Safety. You should receive both whoever employed them.
How long do I have to raise a defect in Victoria? Ten years from the issue of the occupancy permit, or where none issues, the certificate of final inspection. Home Warranty covers work valued at more than $20,000 up to $400,000, including major defects for up to six years, and applies where the builder is unable or unwilling to fix the work.
Are Hilite’s trades employed? The majority are employed rather than hired job by job, and I project manage them on every job.
Does employing trades guarantee better work? No. There are excellent subcontractors who have worked with the same builder for years. Ask how long the builder has worked with the people who will be in your house.
How do I check a builder or trade is licensed? The building regulator publishes a searchable public register that also lists prosecutions and disciplinary action. It takes about five minutes.
Who do I contact after handover? The builder who holds your contract. Ask before you sign how quickly a return visit usually happens, because that answer differs a great deal between businesses.